Engineering & advisory

CBG EPC and turnkey plant execution

Coordinate engineering, procurement and construction around a defined feedstock basis, clear package boundaries and an agreed commissioning programme.

Discuss this requirement
Illustrative process view

The engineering context

What the assignment needs to resolve

A CBG EPC contract turns a verified project basis into an operating facility through engineering, procurement and construction. The term turnkey only becomes meaningful when the battery limits, owner responsibilities, utilities and acceptance conditions are explicit. Land, grid connection, transport equipment and statutory responsibilities must be identified even where they sit outside the EPC price.

Execution planning connects design releases to manufacturing, civil readiness, delivery, installation and commissioning. A plant can be mechanically complete while feedstock arrangements, power availability or the gas buyer interface are still incomplete. Those external dependencies need to be visible in the programme from the start.

From project basis to operating handover

GateWhat should be readyWhy it matters
Design releaseApproved mass balance, layout, package duties and interface listProcurement follows an agreed basis
Manufacturing releaseDrawings, materials, inspection plan and acceptance requirementsInspection points are built into vendor schedules
Site installationCivil readiness, access, foundations and utility interfacesAvoids delivery damage and repeated handling
CommissioningSafe systems, calibrated instruments, trained team and start-up planMechanical completion becomes controlled operation
Performance acceptanceAgreed feed, stable conditions, measurement boundary and test durationOutput, gas quality and consumption can be assessed fairly

Altpreneur scope

How we approach the work

01

Engineering

Develop the process layout and coordinate civil, mechanical, piping, electrical and instrumentation packages. Confirm maintainability, material handling and emergency access.

02

Procurement

Place equipment orders against approved duties and specifications. Manage vendor drawings, inspection points, logistics and long-lead items.

03

Construction and installation

Sequence foundations, structures, equipment erection, piping and electrical works with site readiness and quality documentation.

04

Commissioning and handover

Complete mechanical checks, functional trials, biological start-up and gas-quality validation. Conduct performance testing against the agreed feedstock and operating conditions.

Decisions worth getting right

Distinguish trial operation from guaranteed performance

A short demonstration of gas generation does not establish sustained output. The acceptance protocol should define the averaging period, inlet conditions, allowable interruptions and correction method.

Use a scope matrix alongside the price

For every interface, identify who designs, supplies, installs, tests and maintains it. This reduces disputes about gaps that are not apparent in a summary machinery list.

Prepare the operating handover

As-built drawings, equipment manuals, spare lists, calibration records, emergency procedures and training records are operating assets. Their delivery should be tracked with the physical works.

Assignment outputs

What you receive

  • Approved engineering and procurement packages
  • Construction and installation records
  • Commissioning procedures and test reports
  • As-built information, operating manuals and training
  • Handover and defect-closure documentation

To begin

Useful starting information

  • Site possession and land details
  • Approved capacity and feedstock basis
  • Utility, offtake and financing status
  • Client/EPC responsibility boundaries

Scope and responsibility

Land, utility connections, statutory fees, transportation assets, working capital and taxes require explicit allocation. Biological stabilisation and performance tests need agreed feedstock quality and client readiness.

Common questions

Does turnkey mean every expense is included?

Only the signed scope defines inclusion. Offsite utilities, land, fees, gas logistics and taxes should be individually addressed.

Can a plant guarantee be unconditional?

Performance must refer to measurable feedstock quality, quantity, utility availability, operating hours, gas quality and test duration.

Evidence & further reading

Source material

  1. US EPA AgSTAR: Project Development Handbook
  2. US EPA AgSTAR: Anaerobic Digester/Biogas System Operator Guidebook

Technical references inform the discussion. Final design, operating limits and policy eligibility depend on the project and applicable current documents.